My view is acceptance criteria comes first. Because when the user stories are taken up for discussion and explanation, the objective of the story is initially set up and acceptance criteria is also defined and given to the development team. Based on that- the team, in the second part of the sprint planning meeting, will identify the detailed tasks and comes out with proper estimations.
Which action comes first? Is it Acceptance criteria of user story or tasks of user story in Sprint planning session?
When product owner express the userstories, scrum team asks for clarification for better understanding.What is the order of actions in sprint planning, is it that tasks of particular user story should be entered in in scrum board or acceptance criteria of the user should be defined first and then entering the details of develeopment tasks with the estimates derived? can you help me with this?